Identify the missing word in the following sentence. The purpose of the [?] theme is to identify, assess and control uncertainty.
A. Plans
B. Risk
C. Quality
D. Change
正解:B
質問 2:
Which is a task of product-based planning?
A. Prepare the schedule
B. Analyze the risks
C. Create the product flow diagram
D. Design the plan
正解:C
質問 3:
When considering risks, which describes an opportunity in a project?
A. An event that has occurred resulting in a favourable impact on objectives
B. An uncertain event that could have a favourable impact on objectives
C. An event that has occurred resulting in a negative impact on objectives
D. An uncertain event that could have a negative impact on objectives
正解:B
質問 4:
What takes place during the Closing a Project process?
A. The project closure notification is reviewed and approved
B. An End Stage Report is prepared for the final stage
C. The post-project benefits reviews are performed
D. Ownership of the project's products is transferred to the customer
正解:D
質問 5:
Who carries out audits that are independent of the project?
A. Project Support
B. Project Assurance
C. Quality assurance
D. Project Manager
正解:C
質問 6:
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
A. Controlling a Stage
B. Managing a Stage Boundary
C. Directing a Project
D. Starting up a Project
正解:A
質問 7:
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
A. open issues and risks
B. the handover of products
C. the release of resources
D. the measurement of benefits NOT yet realized
正解:A
質問 8:
Which is an objective of the Managing Product Delivery process?
A. Report progress to the Project Board
B. Ensure that work on products is authorized and agreed with the team
C. Ensure the Business Case is kept under review
D. Sign-off completed Work Packages
正解:B
質問 9:
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
A. Executive
B. Senior Supplier
C. Senior User
D. Corporate/programme management
正解:D