What is not an activity of Contract management?
A. agreeing on how the information manager is to communicate with the IT director
B. monitoring whether the supplied IT-services correspond to the agreed services
C. changing the time of delivery of a change
正解:C
質問 2:
What is a result of the process Specify information requirement?
A. an approved test strategy
B. a list of functional and non-functional demands
C. a functional design
正解:B
質問 3:
Which process is responsible for writing a quality plan for the information provisioning?
A. Review and testing
B. Planning and resource management
C. Demand management
正解:A
質問 4:
What is not an activity of the Change management process?
A. determining the impact of a suggested change to other business processes
B. requesting an impact analysis from an IT service provider
C. analysis of the necessity of a suggested change
正解:B
質問 5:
Which activity does not belong to Business data management?
A. informing end users about changes in data
B. providing reports about management parameters
C. defining data definitions
正解:A