Which of the following is a review process activity?
A. Developing a test plan
B. Executing test scripts
C. Writing test conditions
D. Individual preparation
正解:D
質問 2:
Which statement about combinations of inputs and preconditions is true for a large system?
A. It is easy to test them all in a short time
B. It is not practically possible to test them all
C. It is essential to test them all in order to do good testing
D. It is not possible to test any of them
正解:B
質問 3:
Which one of the following best describes risk-based testing?
A. Fixing as many defects as possible before go-live
B. Targeting testing at the more critical areas of the system
C. Making full use of formal test case design techniques
D. Testing as much of the system as possible in the time available
正解:B
質問 4:
Which of the following activities should be considered before purchasing a tool for an organization?
a) Ensure that the tool does not have a negative impact on existing test processes.
b) Produce a business justification examining both costs and benefits.
c) Determine whether the vendor will continue to provide support for the tool.
d) Introduce tool deployment activities into the testing schedule.
A. b and c
B. c and d
C. a and c
D. a and d
正解:A
質問 5:
Which of the following test activities are more likely to be undertaken by a test lead rather than a tester?
a) Create test specifications.
b) Schedule tests.
c) Define metrics for measuring test progress.
d) Prepare and acquire test data.
A. b and c
B. a and b
C. c and d
D. b and d
正解:A
松本** -
BH0-010試験に合格できました。本当に助けになりました。
問題はなぜか本番試験にほぼ出てて、高いスコアで合格するには十分ですね。