When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure would you use to process the problem in order to create a solution that is feasible from a requirements planning perspective?
A. Interactive single-item planning for the delayed assembly
B. Multi-level single-item planning with the simulation mode option
C. Total planning online
D. Multi-level single-item planning with the display results before saving option
正解:B
質問 2:
Which of the following features are offered by MRP Areas (Material Requirements Planning Areas)? (Choose two.)
A. A storage location may be assigned to different MRP Areas.
B. An MRP Area may include different storage locations.
C. Subcontracting is supported by MRP Areas.
D. Make-to-order production is supported by storage location MRP Areas.
正解:B,C
質問 3:
In what order are the individual steps of material requirements planning performed in SAP ECC?
A. 1. Calculation of safety stock2. Application of the lot-sizing procedure 3. Scheduling4. Determination of the procurement type
B. 1. Net requirements calculation2. Application of the lot-sizing procedure 3. Scheduling4. Determination of the procurement type
C. 1. Availability check2. Application of the lot-sizing procedure3. Determination of the procurement type 4. Scheduling
D. 1. Net requirements calculation2. Application of the lot-sizing procedure3. Determination of the procurementtype4. Scheduling
正解:D
質問 4:
A project team member analyzes the following situation in SAP ECC in the stock/requirements list for a finished product: there is only one customer order and one fixed planned order with a similar quantity amount. The customer order and the planned order both have deadlines on work days but not on the same work day; the planned order has a later deadline. The project team member cannot find a rescheduling message referring to this deadline misalignment in the stock/requirements list. What reasons could there be for the missing message? (Choose two.)
A. The time misalignment falls within the tolerance window defined in Customizing.
B. The requirement coverage element is outside the rescheduling horizon.
C. The elements are linked to each other via fixed pegging.
D. Requirement planning has not yet been carried out to update the rescheduling message.
正解:A,B
質問 5:
A material was planned in the context of SAP ECC material requirements planning and the MRP controller subsequently processed the material by manually converting a specific planned order into a production order. The MRP controller now accesses the current stock/requirements list and the MRP list for this material and compares the two.
Which of the following statements are true for the two lists at this stage? (Choose two.)
A. The stock/requirements list was updated at the precise time it was accessed.
B. The MRP list displays the production order.
C. The MRP list has the status "processed".
D. The stock/requirements list displays the production order.
正解:A,D
質問 6:
Which of the following statements is true for the ATP (available to promise) availability check in SAP ECC that is triggered from a customer order?
A. An availability check by means of ATP creates fixed links between customer orders and their confirmed receipts.
B. The ATP quantity is the quantity still available that can be used to confirm incoming customer orders.
C. If the ATP check establishes non-availability, it checks whether it is still possible to procure or produce in time.
D. The ATP check does not confirm against stocks and receipts, it checks consumption against planning requirements.
正解:B
質問 7:
In modeling in-house production using SAP ECC, bills of material (BOM) are to be recorded in the system. On which business levels can you create a BOM? (Choose two.)
A. At the client level
B. At the business area level
C. At the plant level
D. At the company code level
正解:A,C