Which of the following objects can be generated by a material requirements planning (MRP) run? (Choose two)
A. Sales order
B. Purchase order
C. Purchase requisition
D. Planned order
E. Production order
正解:C,D
質問 2:
Your organization uses the material planning business process.
Which master data lists the steps and the sequence of steps that are necessary to produce a material?
A. Routing
B. Work center
C. Material type
D. Bill of material
正解:A
質問 3:
You perform a completion confirmation on an internally processed operation of a plant maintenance order.
Which of the following functions can be performed during this step? (Choose two)
A. Release the maintenance order
B. Print the shop papers
C. Settle the order
D. Enter the measurement readings
E. Record the actual costs
正解:D,E
質問 4:
What is the purpose of a Warehouse Management transfer order?
A. To move materials between storage bins
B. To move materials between plants
C. To move materials between warehouses
D. To move materials between storage locations
正解:A
質問 5:
Which step in the delivery process integrates with Financial Accounting (FI) and inventory management?
A. Confirm a transfer order
B. Post a goods issue
C. Create a shipment document
D. Generate an invoice
正解:B
質問 6:
Which actions are possible for a production order that is created but not yet released?
A. Material staging can be performed for the production order.
B. Confirmations can be performed for the operations.
C. Material availability checks can be performed.
D. Work in process can be determined.
正解:C
質問 7:
In SAP Enterprise Asset Management, the first step of the corrective maintenance process is to create a notification.
What data is collected in a notification? (Choose two)
A. Activities
B. Actual repair costs
C. Tasks
D. Operations
正解:A,C
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
What is a characteristic of an MRP list used in the material planning business process?
A. The MRP list dynamically reflects manual order changes.
B. Capacity requirements can be viewed from the MRP list.
C. The MRP list has a refresh button.
D. The MRP list is static until the next planning run.
正解:D