Which of the following are characteristics of ECC master production scheduling (MPS)?(Choose three)
A. Non-MPS items can be taken into consideration by an MPS run.
B. The planning of MPS and non-MPS items is always carried out in one planning run.
C. MPS items can be defined on MRP area level.
D. MPS items can be defined on plant level.
E. MPS items are planned in a standard MRP run.
正解:A,C,D
質問 2:
You want to reduce the uncertainty caused by fluctuating requirements for a finished product by using a dynamic safety stock in SAP ECC.
On which specifications is the dynamic safety stock calculation based?
A. The static safety stock per day and the safety time
B. The average daily demand and the safety time
C. The static safety stock and the material forecast
D. The average daily demand and the desired range of coverage
正解:D
質問 3:
What sequence do you follow in master data maintenance to define the production of a material?
A. Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing
B. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing
C. Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
D. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
正解:B
質問 4:
Which of the following items of master data are needed for repetitive manufacturing?(Choose three)
A. Production supply area
B. Production version
C. Product cost collector
D. Repetitive manufacturing profile
E. Master record for serial numbers
正解:B,C,D
質問 5:
What is SAP Solution Manager?
A. An add-on industry solution
B. A managed system in a system landscape
C. A transaction in the SAP ECC system
D. A standalone system that communicates with other systems in a system landscape
正解:D