A customer has set up their department Organizational Breakdown Structure (CBS) and completed the financial settings from the CA Clarity PPM Administration menu. They have also created several departments from the Home menu. However, these new departments are not viewable from the Department CBS browse on projects. Why might this happen?
A. Departments have not been manually added to the Department CBS.
B. Departments have not been assigned a Business Relationship Manager.
C. Departments have not been associated with a service.
D. The locations selected on the projects have not been associated to the department.
正解:D
質問 2:
One of the functions you can perform on the CA Clarity PPM Idea object is to configure the:
A. Chargeback functionality.
B. Baseline.
C. Hierarchy.
D. Incident association.
正解:C
質問 3:
Which action do you typically perform on a Gantt chart?
A. Change the time scale.
B. Synchronize investments.
C. Add virtual attributes.
D. Analyze scenario data.
正解:A
質問 4:
When you use the Assign Resources page to assign a new resource to a project, you notice a resource that is no longer available for your project. You are unable to remove the resource because it has already booked actuals for a task. Which option is available to you?
A. Set the Estimated Time to Complete (ETC) to zero and then remove the resource.
B. Deactivate the resource and delete the resource when the project is completed.
C. Click Replace and assign another resource to take on the remaining work from the original resource.
D. Remove the resource from your team and then remove the resource.
正解:C
質問 5:
When an incident is created, it is visible in one or more of the three tabs on the Incidents list page. Which option correctly identifies the tabs that are visible?
A. Mine, Assigned, and Others
B. Assigned to Me, Reported by Me, and Reported by Others
C. Owned, Team, and Completed
D. Open, Closed, and Resolved
正解:B