Which of the following would NOT be a part of the requirements document that would be presented to a client?
A. Implementation objectives
B. Total cost of ownership
C. Project timeframe
D. Characteristics of paper to be scanned
正解:D
質問 2:
A procedure that allows for the control of the project scope with respect to proposed changes to the plan is known as a:
A. cultural change management procedure.
B. project charter.
C. procurement control plan.
D. change control procedure.
正解:D
質問 3:
One of the largest obstacles when implementing a Document Imaging System (DIS) is:
A. resistance to change.
B. difficulty of use
C. high cost of storage.
D. labor cost.
正解:A
質問 4:
A document that would address the repurposing or reorganization of staff, the benefits of a new system, and the increased market value of staff due to new skills is called a:
A. human resource plan.
B. project management plan.
C. cultural change management plan.
D. project objectives document.
正解:C
質問 5:
A customer wants a comprehensive quote / budget from vendors in response to a Request For Proposal (RFP). The customer wants all elements of the project factored in the quote. What kind of budget model is the customer seeking?
A. Time and materials with cost cap
B. Fixed cost
C. Mixed cost
D. Time and materials
正解:B
質問 6:
A business requires its employees to have access to internal documents via the Internet. Which of the following technologies will allow access to those documents and maintain security of the connection?
A. Virtual Private Network (VPN)
B. Public Key Infrastructure (PKI)
C. Watermarking
D. Checksumming
正解:A