What is the main reason for using a pilot project to introduce a testing tool into an organization? [K1]
A. To make a selection between alternative tools
B. To assess whether the tool will be cost- effective
C. To identify the requirements for using a tool
D. To ensure the tools fits existing processes without change
正解:B
質問 2:
A top-down development strategy affects which level of testing most?
A. User acceptance testing
B. Component testing
C. Integration testing
D. System testing
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Which statement BEST describes when test planning should be performed? [K1]
A. Test planning is performed only once, at the beginning of the life cycle, andgenerates a Master Test Plan
B. Test planning is performed at the beginning of the life cycle and again at the beginning of test execution
C. Test planning is performed at the beginning of the life cycle and again at every test level
D. Test planning is performed continuously in all life cycle processes and activities
正解:D
質問 4:
Which is not the testing objective?
A. Finding defects
B. Preventing defects.
C. Gaining confidence about the level of quality and providing information
D. Debugging defects
正解:D
質問 5:
Which of the following is most likely to cause failure in the implementation of a test tool?
A. No agreed requirements for the tool.
B. The purchase price of the tool.
C. Underestimating the demand for a tool.
D. The cost of resources to implement and maintain the tool.
正解:A
質問 6:
Which of the following statements is most true about test conditions?
A. Applies to software testing only.
B. A testable component derived from business requirements.
C. The grouping of a composite set of test cases which, when tested as a whole, reveal a positive or negative result.
D. An item or event of a component or system that can be verified by one or more test cases.
正解:D
質問 7:
Dynamic Analysis Tools are used to:
A. Find defects, such as memory leaks, while software is executing.
B. Measure the percentage of specific types of code structure that have been exercised.
C. Monitor and report on how a system behaves under a variety of conditions.
D. Determine differences between files or databases.
正解:A
質問 8:
Which is not the fundamental test process?
A. Test closure activities
B. Planning and control
C. Analysis and design
D. None
正解:D
質問 9:
What if the project isn't big enough to justify extensive testing..?
A. Use risk based analysis to find out which areas need to be tested
B. Use automation tool for testing
C. Both a and b
D. None of the above
正解:A