What happens if the appended indicator is not set and an order is appended?
Please choose the correct answer.
Response:
A. Order planned value is multiplied to the WBS element planned value
B. Order planned value increases the WBS element planned value
C. Order planned value is not added to the WBS planned value
D. Order planned value is deducted from the WBS planned value
正解:C
質問 2:
How can material components be assigned to network activities?
There are 3 correct answers to this question.
Response:
A. By assigning them manually
B. Using the bill of materials transfer
C. Using assigned sales orders
D. Using the Internet-based catalog
E. Using ProMan
正解:A,B,D
質問 3:
What is the transaction code for editing the planning profile?
Please choose the correct answer.
Response:
A. OPDS
B. OPSB
C. OPSS
D. OPSC
正解:B
質問 4:
Which account assignment category is important for non-valuated project stock with WBS and sales order item?
Please choose the correct answer.
Response:
A. Q = quantities and values managed in projects
B. E = quantities and values managed in the sales order item
C. G = plant stock, values managed using projects
D. D = quantities managed using sales order item and values managed in projects
正解:D
質問 5:
When you assign material components using the BOM transfer function, the system uses the Reference Point field in the BOM items and activities to establish a logical connection between which items?
There are 2 correct answers to this question.
Response:
A. Network activities
B. Multiple BOM items
C. Multi level BOM
D. Individual BOM items
正解:A,D