Which process provides the Project Board with the information it requires in order to commit
resources to the project?
A. Controlling a Stage
B. Initiating a Project
C. Managing Product Delivery
D. Directing a Project
正解:B
質問 2:
Which risk response type is appropriate to respond to an opportunity?
A. Exploit
B. Fallback
C. Accept
D. Transfer
正解:A
質問 3:
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
A. Controlling a Stage
B. Managing a Stage Boundary
C. Directing a Project
D. Starting up a Project
正解:A
質問 4:
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1.Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
2. Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,
A. Both 1 and 2 are true
B. Neither 1 or 2 are true
C. Only 2 is true
D. Only 1 is true
正解:B
質問 5:
Which is NOT included in the PRINCE2 definition of a project?
A. A project is part ofbusiness as usual'
B. A project is based on an agreed Business Case
C. A project is a temporary organization
D. A project's purpose is to deliver one or more business products
正解:A
質問 6:
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
A. Controlling a Stage
B. Managing a Stage Boundary
C. Directing a Project
D. Closing a Project
正解:B
質問 7:
Which describes risk probability?
A. Level of risks which the project can tolerate before escalating to the Project Board
B. A measure of the likelihood of the risk occurring
C. Probable effect on the project delivering its objectives
D. Timeframe within which the risk may occur
正解:B
質問 8:
Who carries out audits that are independent of the project?
A. Project Support
B. Project Assurance
C. Quality assurance
D. Project Manager
正解:C
質問 9:
Identify the missing words in the following sentence. A Change Authority may be given a [?] to enable it to finance new requirements.
A. risk budget
B. cost tolerance
C. scope tolerance
D. change budget
正解:D
Ootsu -