A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint.
What is the most likely reason that the team did not meet the Sprint objectives?
A. The team is over-worked.
B. The team is lacking skills.
C. The Product Owner is unable to prioritize.
D. The team did not plan the Sprint effectively.
正解:D
質問 2:
Which is a statement of value as described in the Agile manifesto?
A. We value responding to change to satisfy the customer.
B. We value processes and tools over comprehensive documentation.
C. We value customer collaboration over responding to changes.
D. We value project management over individuals and interactions.
正解:A
質問 3:
Which means of communication is the most preferable to clarify the interpretation of a requirement?
A. Telephone
B. E-mail
C. Instant messaging
D. Face-to-face
正解:D
質問 4:
A team is trying to convince a customer about the value of adopting Scrum. The customer likes some of the features of the methodology like the bi-weekly demonstration, but the customer remains largely unconvinced of the value of Scrum and refuses to change the way of working,
What should the team do?
A. Use Scrum and convince the customer during the process.
B. Let the Scrum Master 'translate' to Waterfall practices.
C. Do not follow Scrum until the customer is convinced of the value.
正解:C
質問 5:
What is the primary responsibility of a Scrum Master in order to keep a Scrum team working at its peak level of productivity?
A. Keeping high priority features at the top of the Product Backlog.
B. Not allowing changes to the Product Backlog once the Sprint begins.
C. Supporting the team's decisions and resolving the team's issues.
正解:C
質問 6:
During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.
What is the velocity of the team?
A. 31
B. 24.5
C. 18
正解:C