When is testing complete?
A. When time and budget are exhausted.
B. When there are no remaining high priority defects outstanding.
C. When every data combination has been exercised successfully.
D. When there is enough information for sponsors to make an informed decision about release.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Which of the following is a valid reason for writing test cases based on experience and intuition? [K1]
A. Use of formal techniques requires expensive training
B. Tests based on experience and intuition can supplement formal techniques
C. Formal techniques require the use of expensive tools
D. Only experience can ensure all functionality is covered
正解:B
質問 3:
Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed.
Based on the chart above, what is the most appropriate next test phase? 1 credit
A. Acceptance testing to verify operational requirements
B. Requirements testing as part of testing regulatory compliance
C. Another system test cycle to verify defect resolution
D. Acceptance testing to verify the business process
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Which of the following team roles would be most appropriate to enhance the team and why? 2 credits
A. A person with in-depth technical skills
B. A quality assurance officer
C. A person with the ability to complete tasks
D. A person who brings new ideas to the team
正解:D
質問 5:
As a result of the RAD based development approach, the test manager has decided to change the risk mitigation approach. Which test technique might be most appropriate to use? 2 credits
A. Decision Table Testing
B. Boundary Value Analysis
C. Error Guessing
D. Exploratory Testing
正解:D
質問 6:
Tools like change Man, Clear case are used as..?
A. configuration management tools
B. performance testing tools
C. none of the above
D. functional automation tools
正解:A
質問 7:
Which of the following is not a part of the Test Implementation and Execution Phase?
A. Executing test cases either manually or by using test execution tools
B. Designing the Tests
C. Comparing actual results
D. Creating test suites from the test cases
正解:B
質問 8:
Which of the following does NOT represent one of the three triggers for maintenance testing an operational system?
A. Introduction of a test management tool
B. System modification
C. System retirement
D. Data migration
正解:D
質問 9:
An input field takes the year of birth between 1900 and 2004. The boundary values for testing this field are:
A. 1900, 2004
B. 1899, 1900, 1901,2003,2004,2005
C. 1899,1900,2004,2005
D. 0,1900,2004,2005
正解:C
Ono -