Continually measuring and monitoring the actual cost versus the budget is done to:
A. smooth out the variances.
B. approve the variances.
C. generate reports.
D. analyze the reasons for variances.
正解:D
質問 2:
Which of the following are components of the latest estimate in PRS (Profitability Reporting System)?
A. Actual results of the previous period.
B. Sales, cost of sales and gross profit.
C. Baseline, ETC and EAC.
D. Sales, volumes and cost of sales.
正解:B
質問 3:
What is the definition of project Risk Management?
A. To manage risks that will enable Nokia to profitably grow the business, while having a basic understanding of the risks and responses required.
B. To take risks that will enable Nokia to profitably grow the business while having a thorough understanding of the risks and responses required for its success.
C. To avoid risks that would damage the desired growth in sales and profitability while taking all opportunities to positively influence customer satisfaction.
D. To maximize the probability and consequences of positive events and minimize the probability and consequences of adverse events to project objectives.
正解:D
質問 4:
In 4C internal resources are planned as:
A. monetary value.
B. man working days (MWD).
C. not planned.
D. headcount.
正解:B
質問 5:
The technique of analyzing the sequence of activities with the least amount of scheduling flexibility is called the:
A. critical path method.
B. Precedence diagram method.
C. Work breakdown Structure.
D. flowchart.
正解:A