Project team members are located in two different time zones, with a five hour time difference. The team members cannot agree on a time of day to have a standing meeting. Which of the following is the BEST approach to finding a meeting time?
A. Forcing
B. Compromising
C. Smoothing
D. Avoiding
正解:B
質問 2:
The project manager has received an approved change request. Which of the following actions should the project manager take NEXT?
A. Develop a plan to incorporate the change into the project
B. Schedule a meeting with the change advisory board to discuss the impact of the change
C. Perform a probability and impact assessment on the approved change
D. Hold a team meeting to ensure the change is immediately implemented
正解:A
質問 3:
A key supplier has informed the project manager that there will be a two month delay to fulfill an order. Which component of the project plan is affected and which of the following actions should be taken?
A. Evaluate the project schedule and raise a project issue.
B. Manage scope and consider a project change request.
C. Implement approved changes by utilizing a change management form.
D. Manage project quality and schedule a meeting.
正解:A
質問 4:
Which of the following BEST describes a project risk?
A. Something that will negatively impact the project
B. Something that may positively or negatively impact the project
C. Something that is outside of the control of the project manager
D. Something that has already affected the project
正解:B
質問 5:
The project team is not comfortable moving an expensive material. A third party is hired to move the material. This is an example of risk:
A. Acceptance
B. Sharing
C. Transference
D. Avoidance
正解:C
質問 6:
An organization has developed a project that will be taking place in a volatile climate. Which of the following aspects of the project plan will be affected, and what action should the project manager take?
A. Risk management; create a risk matrix
B. Scope management; complete a communications plan
C. Cost management; prepare a budget analysis
D. Work performance information; implement a WBS
正解:A