Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
A. Quantitative risk analysis
B. Risk management planning
C. Risk identification
D. Qualitative risk analysis
正解:D
質問 2:
Which of the following is a complete set of indexed contract documentation, including the closed contract?
A. Procurement file
B. Procurement management plan
C. Procurement package
D. Negotiated settlements
正解:A
質問 3:
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?
A. Enhance
B. Share
C. Exploit
D. Transfer
正解:D
質問 4:
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
A. Control Scope
B. Create WBS
C. Define Scope
D. Collect Requirements
正解:D
質問 5:
Which quality control technique illustrates the 80/20 principle?
A. Control chart
B. Ishikawa diagram
C. Run chart
D. Pareto chart
正解:D
質問 6:
Which of the following is an input of the Define Activities process?
A. Milestone list
B. Resource calendars
C. Activity list
D. Scope baseline
正解:D
質問 7:
Which action is included in the Control Costs process?
A. Monitor cost performance to isolate and understand variances from the approved cost baseline
B. Identify how the project costs will be planned, structured, and controlled
C. Determine policies, objectives, and responsibilities to satisfy stakeholder needs
D. Develop an approximation of the monetary resources needed to complete project activities
正解:A
質問 8:
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
A. 0.5
B. 1
C. 0.8
D. 0.4
正解:C
質問 9:
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
A. Determine Budget
B. Estimate Activity Resources
C. Control Costs
D. Estimate Costs
正解:B