Which of the following is an input to Control Scope?
A. Project document updates
B. Project schedule
C. Work performance information
D. Organizational process assets updates
正解:D
質問 2:
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
A. Direct and Manage Project Work
B. Plan Quality Management
C. Monitor and Control Project Work
D. Develop Project Management Plan
正解:D
質問 3:
What is the responsibility of the project manager andthe functional manager respectively?
A. Achieving the project objectives; providing management oversight for an administrative area
B. A facet of the core business; achieving the projectobjectives
C. Oversight for an administrative area; a facet of the core business
D. Both are responsible for achieving the project objectives.
正解:A
質問 4:
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
A. Reserve analysis
B. Analogous estimating
C. Parametric estimating
D. Three-point estimating
正解:B
質問 5:
Which of the following is a component of three-point estimates?
A. Probabilistic
B. Expected
C. Anticipated
D. Most likely
正解:D