Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
A. All levels of management
B. Only corporate or programme management
C. Only the Project Board
D. Only the Project Manager
正解:A
質問 2:
According to the 'continued business justification' principle, what should happen to the funds when a project can no longer be justified?
A. They should be used to deliver a reduction in the scope of the project
B. They should be transferred back to the project board to reassign
C. They should be returned to corporate, programme management or customer
D. They should be used to create an alternative business case for the project
正解:C
質問 3:
Which plan provides the Business Case with costs during the Initiating a Project process?
A. Project Plan
B. Stage Plan
C. Initiation Stage Plan
D. Team Plan
正解:A
質問 4:
Which document should record the agreed amount of risk budget for a project?
A. Risk Register
B. Project Plan
C. Project Brief
D. Risk Management Strategy
正解:B
質問 5:
Which statement about the quality review technique is FALSE?
A. It defines the quality responsibilities of the project team
B. It enables a check to be made on a product's fitness for purpose
C. It is used to gain wider acceptance of a product by involving key interested parties
D. It supports the management of future changes by providing a baseline for a product
正解:A
質問 6:
Which is an objective of the Starting up a Project process?
A. Agree how the project will be monitored and controlled after initiation
B. Agree how issues and changes will be identified, assessed and controlled
C. Authorize the Project Manager to proceed with the initiation stage
D. Identify who will be responsible for creating the Project Plan
正解:D
質問 7:
Which principle helps to ensure that all changes to the outputs are agreed?
A. Focus on products
B. Learn from experience
C. Manage by exception
D. Defined roles and responsibilities
正解:D
質問 8:
Which describes risk probability?
A. Level of risks which the project can tolerate before escalating to the Project Board
B. A measure of the likelihood of the risk occurring
C. Probable effect on the project delivering its objectives
D. Timeframe within which the risk may occur
正解:B