Which of the following project management team roles can be shared?
1.Project Assurance
2.Executive
3.Senior User
4.Senior Supplier
A. 1,2,4
B. 2,3,4
C. 1,3,4
D. 1,2,3
正解:C
質問 2:
Which product would be at the centre of any impact assessment of risks, issues and changes?
A. Communication Management Strategy
B. Business Case
C. Highlight Report
D. Lessons Log
正解:B
質問 3:
Which of the following describes a situation when an Issue Report would be produced?
A. Every time someone wishes to bring anything to the attention of the Project Manager
B. When ever the Project Board direct the Project Manager
C. Only if the Project Manager feels it is necessary
D. It is only created for those issues that need to be handled formally
正解:D
質問 4:
Are the following statements regarding the Communication Management Strategy true?
1.Defines how and where the project's products will be stored
2.Contains a description of the means and frequency of communication to parties both internal and external to the project
A. Both 1 and 2 are false
B. Both 1 and 2 are true
C. Only 2 is true
D. Only 1 is true
正解:C
質問 5:
Identify the missing word(s) in the following sentence... The purpose of the Closing a Project process is to provide a fixed point at which acceptance for the [?] is confirmed.
A. Project mandate
B. Project scope
C. Project product
D. Final project cost
正解:C
質問 6:
Which statement describes risk cause?
A. The area of uncertainty in terms of the threat or opportunity
B. The impact of a risk on the stage and project tolerance
C. How likely a risk is to occur in a given project situation
D. The situation or event that gave rise to a risk
正解:D
質問 7:
Which of the following would be done once the Project Board have authorized initiation?
A. Define how the project will deliver the chosen business solution
B. Establish who needs information, when and in what format
C. Create the initiation Stage Plan
D. Establish the quality expectations of the customer
正解:B