What is a purpose of a Daily Log?
A. Provide a regular update to the Project Board on the progress of the stage
B. Record the products and activities planned for the stage
C. Record actions taken to recover from issues NOT recorded in the Issue Register
D. Record and track the status of all products produced during a stage
正解:C
質問 2:
Which of the following is considered to be an output of a PRINCE2 project?
A. Any tangible or intangible specialist product
B. A consequence of doing the project that is perceived as negative by one or more stakeholders
C. A measurable improvement to the business
D. The result of change, normally affecting real world behaviour
正解:A
質問 3:
Which product would be updated to show that a decision has been made on an off-specification which has now been closed?
A. Risk Register
B. Issue Report
C. Daily Log
D. Quality Register
正解:B
質問 4:
The reviewer(s) and approver(s) of a particular product are identified in which of the following?
A. The quality criteria
B. The Project Initiation Documentation
C. The Quality Management Strategy
D. The product's related Product Description
正解:D
質問 5:
Which process is largely about preventing poorly conceived projects from ever being initiated?
A. Initiating a Project
B. Directing a Project
C. Closing a Project
D. Starting Up a Project
正解:D
質問 6:
Which is NOT established as part of the Starting Up a Project process?
A. A Plan for the work of initiation
B. Information on the various ways the project can be delivered
C. A description of what the project is to deliver
D. A plan for how and when a measurement of the achievement of the project's benefits can be made
正解:D
質問 7:
Which is a specific responsibility of Project Assurance?
A. Approving the Risk Management Strategy
B. Giving ad-hoc direction to the Project Manager
C. Reporting highlights to the Project Board
D. Ensuring the right people are planned to be involved in quality inspection
正解:C