Which is a purpose of a quality register?
A. To identify corrective actions that are required after an audit by quality assurance
B. To issue a unique reference number for each product
C. To detail the number and type of quality activities to be conducted
D. To record the quality management approach for a product
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Which describes risk probability?
A. Level of risks which the project can tolerate before escalating to the Project Board
B. A measure of the likelihood of the risk occurring
C. Probable effect on the project delivering its objectives
D. Timeframe within which the risk may occur
正解:B
質問 3:
What is the minimum number of management stages required by PRINCE2?
A. Two stages: to initiate and to deliver the project
B. Four stages: to start, to initiate, to deliver and to close the project
C. One stage: to cover the whole project
D. Three stages: to initiate, to deliver and to close the project
正解:A
質問 4:
What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?
A. Statements of actual versus forecast benefits at reviews
B. No specific documents related to benefits are necessary
C. The management actions needed to ensure benefits are realized
D. The senior user's responsibilities for realizing benefits
正解:D
質問 5:
According to the 'tailor to suit the project' principle, what is the basis for effective project management?
A. That the project is divided into an appropriate number of stages
B. That the appropriate information is provided to make decisions
C. That the appropriate number and type of meetings are held
D. That the project method relates to the project's environment
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Which is a minimum requirement when applying the business case theme?
A. To integrate the benefits management approach with the project and stage plans
B. To specify the solution to be used to deliver the business option selected
C. To ensure the corporate business plan is updated with the project costs and benefits
D. To define the management actions required to ensure the project's outcomes are achieved
正解:B