最新なPRINCE2 PRINCE2Practitioner問題集(285題)、真実試験の問題を全部にカバー!

Pass4Testは斬新なPRINCE2 PRINCE2 Certification PRINCE2Practitioner問題集を提供し、それをダウンロードしてから、PRINCE2Practitioner試験をいつ受けても100%に合格できる!一回に不合格すれば全額に返金!

  • 試験コード:PRINCE2Practitioner
  • 試験名称:PRINCE2 Practitioner Exam
  • 問題数:285 問題と回答
  • 最近更新時間:2024-04-16
  • PDF版 Demo
  • PC ソフト版 Demo
  • オンライン版 Demo
  • 価格:12900.00 5999.00  
質問 1:
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage.
Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Which 2 statements should be recorded under the Expected dis-benefits heading?
A. The project will take two years to deliver.
B. Staff morale will be negatively affected.
C. Staff may lose the opportunity to work in Information Technology.
D. MFH will lose direct control over the outsourced business functions.
E. An investment of £2.5m is required.
正解:A,D

質問 2:
Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PID). The PID includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Information needs for each interested party section?
A. Move entry 13 to Tools and techniques because it describes the method to be used to communicate to the individual producing the staff newsletter.
B. Delete entry 14 because this relates to the development of a particular product and should be recorded under Development interfaces within the relevant Work Package.
C. Delete entry 13 because the activity to provide the weekly updates should be scheduled in the relevant Stage Plan.
正解:B

質問 3:
Additional Information
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.

正解:

Explanation


質問 4:
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
There is a major concern over an apparent lack of control of project documentation.
For each concern listed in Column 1, select from Column 2 the configuration management task that could help address the problem. Each selection from Column 2 can be used once, more than once or not at all.

正解:

Explanation


質問 5:
During a work package the Team manager needs to keep the project manager informed, which management product is used for this?
A. Highlight report
B. End Stage Report
C. Issue Report
D. Checkpoint Report
正解:D

質問 6:
Scenario
Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago.
She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed business assurance for this project?
A. Add Outcome Consultants' because they carried out the feasibility study.
B. Remove because he will be impacted by the project and therefore represents a user.
C. Retain because he is familiar with the Ministry of Food Hygiene business strategy, the business level risk assessment and the Business Case standards.
D. Add 'Director of Finance Division' because she is responsible for checking that any supplier and contractor payments are authorized.
E. Replace with 'Project Manager' because this is a simple project that does not require additional business assurance.
正解:C,D

弊社のPRINCE2Practitioner問題集のメリット

Pass4Testの人気IT認定試験問題集は的中率が高くて、100%試験に合格できるように作成されたものです。Pass4Testの問題集はIT専門家が長年の経験を活かして最新のシラバスに従って研究し出した学習教材です。弊社のPRINCE2Practitioner問題集は100%の正確率を持っています。弊社のPRINCE2Practitioner問題集は多肢選択問題、単一選択問題、ドラッグ とドロップ問題及び穴埋め問題のいくつかの種類を提供しております。

Pass4Testは効率が良い受験法を教えてさしあげます。弊社のPRINCE2Practitioner問題集は精確に実際試験の範囲を絞ります。弊社のPRINCE2Practitioner問題集を利用すると、試験の準備をするときに時間をたくさん節約することができます。弊社の問題集によって、あなたは試験に関連する専門知識をよく習得し、自分の能力を高めることができます。それだけでなく、弊社のPRINCE2Practitioner問題集はあなたがPRINCE2Practitioner認定試験に一発合格できることを保証いたします。

行き届いたサービス、お客様の立場からの思いやり、高品質の学習教材を提供するのは弊社の目標です。 お客様がご購入の前に、無料で弊社のPRINCE2Practitioner試験「PRINCE2 Practitioner Exam」のサンプルをダウンロードして試用することができます。PDF版とソフト版の両方がありますから、あなたに最大の便利を捧げます。それに、PRINCE2Practitioner試験問題は最新の試験情報に基づいて定期的にアップデートされています。

一年間無料で問題集をアップデートするサービスを提供します。

弊社の商品をご購入になったことがあるお客様に一年間の無料更新サービスを提供いたします。弊社は毎日問題集が更新されたかどうかを確認しますから、もし更新されたら、弊社は直ちに最新版のPRINCE2Practitioner問題集をお客様のメールアドレスに送信いたします。ですから、試験に関連する情報が変わったら、あなたがすぐに知ることができます。弊社はお客様がいつでも最新版のPRINCE2 PRINCE2Practitioner学習教材を持っていることを保証します。

PRINCE2 PRINCE2Practitioner 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Understand The Principles Underpinning These Elements
トピック 2
  • PRINCE2 Products And Can Apply This Understanding
トピック 3
  • Demonstrate Their Ability To Tune PRINCE2 To Different Project Circumstances
トピック 4
  • Demonstrate That They Understand The Reasons Behind The Principles, Themes And Processes Of PRINCE2

参照:https://www.prince2.com/usa/prince2-examination-format

弊社は無料でPRINCE2 Certification試験のDEMOを提供します。

Pass4Testの試験問題集はPDF版とソフト版があります。PDF版のPRINCE2Practitioner問題集は印刷されることができ、ソフト版のPRINCE2Practitioner問題集はどのパソコンでも使われることもできます。両方の問題集のデモを無料で提供し、ご購入の前に問題集をよく理解することができます。

簡単で便利な購入方法ご購入を完了するためにわずか2つのステップが必要です。弊社は最速のスピードでお客様のメールボックスに製品をお送りします。あなたはただ電子メールの添付ファイルをダウンロードする必要があります。

領収書について:社名入りの領収書が必要な場合には、メールで社名に記入して頂き送信してください。弊社はPDF版の領収書を提供いたします。

弊社のPRINCE2 Certification問題集を利用すれば必ず試験に合格できます。

Pass4TestのPRINCE2 PRINCE2Practitioner問題集はIT認定試験に関連する豊富な経験を持っているIT専門家によって研究された最新バージョンの試験参考書です。PRINCE2 PRINCE2Practitioner問題集は最新のPRINCE2 PRINCE2Practitioner試験内容を含んでいてヒット率がとても高いです。Pass4TestのPRINCE2 PRINCE2Practitioner問題集を真剣に勉強する限り、簡単に試験に合格することができます。弊社の問題集は100%の合格率を持っています。これは数え切れない受験者の皆さんに証明されたことです。100%一発合格!失敗一回なら、全額返金を約束します!

919 お客様のコメント最新のコメント

Aoyama - 

問題集PRINCE2PractitionerのPDFバージョンは非常に明確です。PRINCE2Practitioner問題集を所有する価値があります!

Matsumura - 

一部のPRINCE2Practitioner問題集は実際の試験とは異なりますが、知識をさらに強化して試験に合格しました。

栋方** - 

より効率良く合格を目指す私のための,必携のPRINCE2Practitioner試験対策書だと思う。理解しやすいPRINCE2Practitioner参考書だ。ありがとうございます

Suho - 

早速勉強していきたいと思います!。ここで感謝を申し上げます。ありがとうございました。

Sakamoto - 

やっと合格できた!
こんな俺が1ヵ月の勉強のみで合格できたので
是非参考にして合格し就活や転職の成功の足しにしてくれ。

斉藤** - 

PRINCE2Practitionerに合格しました。また次回もここにお世話になりたいと思います。

Fujimori - 

順調にPRINCE2Practitioner試験をパスしました。今後ともよろしくお願い申し上げます。

Ogawa - 

ありがとねPass4Testさんまた、図解を豊富に取り入れて、知識を整理できるようにしました。PRINCE2Practitionerの問題集、今までの出会いで一番いい問題集でした。

Yamada - 

Pass4Testの問題集の新鮮のところは、図解を豊富に取り入れて、知識を整理できるように工夫しています。

鹤海** - 

このPRINCE2Practitioner問題集のみ、勉強時間は会社の往復の電車の中、アプリバージョンで、平日1時間ちょいでした。

Kojima - 

一生懸命頑張ってよかったです!無事にPRINCE2Practitionerを合格できました!本当に有難うございました。

Mio - 

今時のアプリを利用した過去問演習にも対応
至れり尽くせりのPRINCE2Practitioner一冊だなって思いました。

寺本** - 

PRINCE2Practitioner問題集は専門的な知識です。また、PRINCE2Practitioner問題集の的中率が高いです。その二つ点で、PRINCE2Practitioner試験に合格することは簡単です。

Katou - 

問題集はなぜ素敵て言うと、やっぱり詳細な解説付きだよな。今回もお世話になりました。PRINCE2Practitionerに合格です
ありがとう

高田** - 

本格的なPRINCE2Practitioner問題も掲載されてるし、索引も充実!このPass4TestのPRINCE2Practitioner問題中心にすすめるのをおすすめ。

Watanabe - 

PRINCE2Practitioner知っておくべき内容が簡潔に説明されているので
効率的に知識を得ることができます。

森尾** - 

ソフトとアプリがもらえて、内容も濃く、問題や擬似問題集と回答などもあり

Hayasaka - 

PRINCE2Practitioner合格しました。また次回PRINCE2-Foundationもここにお世話になりたいと思います。

メッセージを送る

あなたのメールアドレスは公開されません。必要な部分に * が付きます。

Pass4Test問題集を選ぶ理由は何でしょうか?

品質保証

Pass4Testは試験内容に応じて作り上げられて、正確に試験の内容を捉え、最新の97%のカバー率の問題集を提供することができます。

一年間の無料アップデート

Pass4Testは一年間で無料更新サービスを提供することができ、認定試験の合格に大変役に立ちます。もし試験内容が変われば、早速お客様にお知らせします。そして、もし更新版がれば、お客様にお送りいたします。

全額返金

お客様に試験資料を提供してあげ、勉強時間は短くても、合格できることを保証いたします。不合格になる場合は、全額返金することを保証いたします。

ご購入の前の試用

Pass4Testは無料でサンプルを提供することができます。無料サンプルのご利用によってで、もっと自信を持って認定試験に合格することができます。